A piping system is designed twice. Once for the pressure inside it, and once for the weight and movement outside it. The second design is the support system, and on most projects it is drawn last, bid late and fabricated by whoever has room on the schedule.
That order is backwards, because a support problem does not announce itself the way a weld problem does. The line still holds pressure. It simply sags between hangers, drags a nozzle out of alignment, or grows into a structure that was never meant to take the load. By the time anyone measures it, the pipe is insulated, the platform is built, and the fix costs more than the supports did.
Key Takeaways
- Spacing is the one number the code hands you. ASME B31.1 publishes suggested maximum spans for standard wall steel pipe in water service, from about 7 feet at NPS 1 to 32 feet at NPS 24.
- ASME B31.3 publishes no span table. Process piping has to be supported so that stresses stay inside the code limits; how far apart that puts the supports is the designer’s problem, not a lookup.
- Movement decides the type, not weight. Rigid where the pipe stays put, a variable spring where it moves a little, a constant effort spring where it moves a lot or lands on rotating equipment.
- MSS SP-58 governs the hardware. It covers materials, design, manufacture, selection, application, inspection and installation of pipe hangers and supports; MSS SP-127 is the companion for seismic, wind and dynamic bracing.
- Most supports on an industrial job are fabricated, not bought. Shoes, trunnions, dummy legs, clamps, frames and the steel they land on are drawings, and they belong with the spools they carry.
What a pipe support is actually carrying
Four loads, and they do not arrive together.
The first is deadweight: the pipe, its contents, its insulation and every valve, flange set and instrument hung on it. A six inch line full of water weighs roughly twice what the empty pipe weighs, which is why a system that looked fine during erection can sag the first time it is filled for a test.
The second is thermal movement. Steel grows when it is heated, and a long run between two fixed points grows into whatever is in the way. The support system decides where that growth goes: an anchor stops it, a guide steers it, a rest lets it slide. Getting those three wrong in the same run is how a line ends up pushing against itself.
The third is occasional loading, which includes wind, seismic events, water hammer, slug flow and relief valve reaction. These are short, violent and easy to leave out of a weight calculation.
The fourth is the load the support must not transmit. Pumps, compressors and turbines have published allowable nozzle loads, and piping that leans on a casing pulls shafts out of alignment and shortens bearing life. A good deal of support design exists to keep weight off equipment that cannot take it.
Spacing is the part the code gives you a number for
ASME B31.1, the power piping code, publishes a table of suggested maximum spans between supports for standard wall and heavier steel pipe. The figures below are the water service column. They assume a bending stress of about 2,300 psi and a mid-span sag of roughly a tenth of an inch, with the pipe full.
How far apart
Suggested maximum span between supports, water service
Standard wall steel pipe, full of water, straight run with no concentrated load in the span. Distance in feet.
NPS 1
NPS 2
NPS 4
NPS 8
NPS 12
NPS 16
NPS 24
Source: ASME B31.1 Power Piping, suggested maximum span between supports. Vapor and gas service spans are longer because the pipe carries less weight.
Three things about that table get missed.
It is a straight run figure. Put a valve, a flange set or a bank of instruments in the middle of a span and the concentrated load is no longer covered: that span needs its own calculation or a support under the weight. It is also a deflection limit, not a strength limit. The spacing is set by how much sag the owner will tolerate in a line that has to drain, not by what the pipe can survive.
And it is a maximum, not a target. Insulated lines, lines that can slug, and lines in a corrosive service often get supported closer together than the table allows, because the consequence of a sag is worse than the cost of another support.
B31.1 also sets a floor on the hardware. Hanger rods are a minimum of 3/8 inch for NPS 2 and smaller and 1/2 inch for NPS 2 1/2 and larger, regardless of what the weight calculation says a smaller rod could hold.
ASME B31.3, the process piping code most refinery, chemical and gas processing work is designed to, publishes no equivalent span table. It requires that piping be supported so that the resulting stresses stay within code allowables and that loads are not transmitted to equipment beyond what the equipment can take. That is a performance requirement, and it is the reason two contractors can bid the same isometric with different support counts. If your specification does not say which code governs the supports, it has left a gap that will be filled by whoever is cheapest.
Movement decides the type, not the weight
Once the weight is known, the next question is how far the pipe moves at that point between cold and operating conditions. The answer sorts supports into three families.
Rigid supports are for locations with no appreciable vertical movement: a shoe on a steel beam, a clevis hanger on a rod, a clamp on a riser. They are the cheapest thing on the drawing and should be the default wherever the pipe stays put.
Variable spring hangers carry the load through a coil spring. As the pipe moves up or down the spring compresses or extends, so the load it carries changes by the travel multiplied by the spring rate. That change matters, because the difference between cold load and hot load is load the piping has to absorb somewhere. Most owner specifications cap the change at 25% of the operating load, and tighten it on lines that terminate at rotating equipment.
Constant effort supports use a spring and a lever to hold the load nearly constant through the full travel. They cost more and they are specified where movement is large or where the line lands on a turbine or compressor nozzle that will not tolerate a load swing.
One field item belongs with this: spring supports ship with travel stops pinned in place so the spring does not work during handling and erection. Those stops have to come out before the system goes into service, and the removal has to be recorded. A spring hanger left pinned is a rigid support in the one location the designer decided a rigid support would not do.
What MSS SP-58 covers, and what your drawing still has to say
MSS SP-58 is the standard the hardware is built to. It covers materials, design, manufacture, selection, application, inspection and installation of pipe hangers and supports across the service temperature range, and it sets load ratings and the numbered component types that specifications call out by number. MSS SP-127 is the companion standard for seismic, wind and other dynamic bracing.
What the standard does not do is make the decisions for your line. A support detail still has to state:
- Whether the point is an anchor, a guide, a rest or a hanger, because those four do opposite jobs.
- The design load, the travel and, for springs, the cold and hot loads.
- Insulation thickness and whether the shoe clears it. Shoe height is set by the insulation, and a shoe detailed for two inches on a line that ships with three inches is scrap.
- Materials and isolation. Stainless pipe resting on carbon steel needs an isolator, and a support in a coastal or chemical environment needs the same coating decision the pipe got.
- The attachment detail, which is the subject of the next section.
The attachment is where piping and structure meet
There are two ways to connect a support to a pipe, and they have different consequences.
A clamped attachment grips the pipe. Nothing is welded to the pressure boundary, so nothing about the attachment belongs to the piping code. It is the simpler option, and on thin wall or high alloy pipe it is often the only acceptable one.
A welded attachment, such as a shoe, a trunnion or a dummy leg, is welded directly to the pipe. That weld is on the pressure boundary. It is made to a qualified procedure by a qualified welder, it is inspected to the same rules as the rest of the piping, and the material of the attachment has to be compatible with the pipe it lands on. Carbon steel welded to stainless pipe for convenience is a repair waiting to happen.
The practical point for a buyer: welded attachments are cheapest when they go on in the shop, with the spool on a positioner and the welder standing up. The same attachment welded in the field, overhead, on an erected line, costs several times as much and attracts its own inspection. Deciding attachment details before pipe spool fabrication starts is the difference between a shop weld and a field weld, and that decision is usually made by whoever draws the supports first.
Why supports are a fabrication item, not a purchase order
Catalog hardware covers the clevis hangers, the rods, the springs and the clamps. It does not cover the steel those parts land on, and on an industrial job that steel is most of the package: pipe racks, frames, dummy legs, trunnions, base plates, braces, cantilevers off existing columns and the platforms that let somebody reach the valve.
All of it is made to a drawing. That is why support steel sits naturally with custom metal fabrication rather than with purchasing, and why it is usually quoted alongside miscellaneous metals — the platforms, stairs, handrail and ladders that end up in the same bays and on the same trucks.
LMC Industrial Contractors fabricates piping supports and clamps, structural steel frame supports, equipment supports, temporary support and jacket structures, and access platforms and walkways at its Dansville, New York shop, on the same equipment that cuts and welds the spools: a PythonX CNC plasma cutting system, a Ficep Gemini plate processor, CNC tube benders, and sub arc and automated welders. Structural welding is to AWS D1.1 and D1.5, process piping to the ASME B31 family, with ASME “U”, “S” and “PP” stamps and NBIC “R” for repairs. Blasting and coating are done in house by NACE certified painters and blasters, so supports arrive finished rather than waiting on a painter after erection. The crews that set the structural steel and run the mechanical scope are LMC’s own.
Keeping supports with the spools also fixes a sequencing problem. Supports fabricated separately tend to show up after the pipe is hung on temporary steel, and temporary steel has a way of becoming permanent. The alternative is covered in more detail in our comparison of shop and field process piping fabrication, and it is the same argument that makes modular process skids work: assemble and prove it where the conditions are controlled, then set it.
What belongs in a pipe support bid package
Send these, and the quotes will be comparable
- The governing code for the piping, and the support specification if one exists.
- Isometrics with support locations, types and loads marked, not just the pipe routing.
- A support schedule: mark number, type, design load, travel, cold and hot loads for springs.
- Insulation thickness per line, because it sets shoe height.
- Materials by line, including which lines are stainless and need isolation.
- The coating specification, and who applies it.
- Who supplies the steel the supports land on, and where that scope ends.
- Whether the supports ship with the spools or separately.
The last item decides more of the cost than most buyers expect. A support package quoted with the spools is fabricated, coated and shipped as one lot. Quoted alone, it is a small order of custom steel with its own drawings, its own coating run and its own delivery, and it is priced that way.
Frequently asked questions
How far apart should pipe supports be?
For standard wall steel pipe in water service, ASME B31.1 suggests a maximum of about 7 feet at NPS 1, 14 feet at NPS 4, 19 feet at NPS 8 and 32 feet at NPS 24, based on a bending stress of roughly 2,300 psi and about a tenth of an inch of sag. Those spans assume a straight run with no concentrated load; a valve or a flange set in the span needs its own support. ASME B31.3 process piping has no equivalent table, so spacing follows the stress analysis and the project specification.
What is the difference between a pipe support and a pipe hanger?
A hanger carries the pipe from above, usually on a rod from structure or a spring. A support carries it from below, usually as a shoe resting on steel or concrete. Both are pipe supports in the general sense, and MSS SP-58 covers the hardware for both. The practical difference is what they do with movement: a rest lets the pipe slide, an anchor stops it, a guide allows axial movement while preventing lateral movement.
When do you need a spring hanger instead of a rigid support?
When the pipe moves vertically at that point between cold and operating conditions. A rigid support at a location that lifts will simply unload, leaving the weight somewhere it was not designed to go; a rigid support at a location that drops will take load it was not sized for. A variable spring handles moderate movement, with most specifications capping the load change at 25% of the operating load. Where travel is large, or the line terminates at a turbine or compressor that will not accept a load swing, a constant effort support is specified instead.
What does MSS SP-58 cover?
It is the standard for pipe hangers and supports: materials, design, manufacture, selection, application, inspection and installation across the service temperature range, including load ratings and the numbered component types that specifications reference. MSS SP-127 is the companion standard for seismic, wind and other dynamic bracing. Neither standard chooses the support locations for a given system; that comes from the piping code and the stress analysis.
Can pipe supports be fabricated with the spools?
Yes, and it is usually cheaper. Welded attachments such as shoes, trunnions and dummy legs go on in position in the shop rather than overhead in the field, the support steel is cut and welded on the same equipment, and the whole lot is blasted, coated and shipped together. The requirement is that support details are settled before spool fabrication starts, because adding a welded attachment to a finished spool means cutting into a tested assembly.
Decide the supports with the piping, not after it
Supports are drawn late because they depend on everything else: the route, the insulation, the equipment, the structure. That dependency is real, but it is an argument for settling them earlier, not for leaving them to the end. The questions worth answering before the package goes out are which code governs, where the anchors and guides fall, what moves and how far, who supplies the steel the supports land on, and whether the package ships with the spools.
LMC Industrial Contractors fabricates pipe spools, support steel and the platforms around them in one Dansville, New York shop and installs them with its own crews. Talk to us about your piping package and we will tell you which supports belong in the shop and what that changes about your field schedule.