Miscellaneous Metals: What Is in the Package and Who Owns It

Miscellaneous metals is the part of an industrial project that everyone assumes somebody else is carrying. The structural steel contract covers the frame. The equipment packages cover the machines. In between sit the stairs that reach the platform, the handrail around it, the supports under the pipe and the ladder up the side of the tank. On a lot of jobs none of that steel is priced until the frame is already standing and someone asks how the operators are supposed to get up there.

The package is not technically difficult. It is administratively slippery. It is governed by different rules than the frame, it is detailed last, it is coated differently, and it is the one package whose dimensions are set by a federal safety standard rather than by the engineer’s preference. This guide covers what miscellaneous metals includes, why it falls between contracts, who designs it, and what to put in a bid package so it is priced once instead of three times.

Key Takeaways

  • It is a contract category, not a material. Stairs, ladders, platforms, handrail, guardrail and equipment supports are steel, and they are still not part of the structural steel contract.
  • The standard says so in writing. ANSI/AISC 303 states that structural steel does not include other steel, iron or metal items that are not described in its own scope section, even when those items are shown on the structural drawings.
  • OSHA sets the dimensions. Top rails at 42 inches plus or minus 3, stairs between 30 and 50 degrees, fall protection at 4 feet in general industry. These are not preferences.
  • Caged ladders are on a clock. On fixed ladders over 24 feet, a cage has not counted as fall protection for new installations since November 19, 2018, and every such ladder needs a fall arrest or ladder safety system by November 18, 2036.
  • The bid package decides the price. Name the items, name the governing standard for each one, and say who carries the delegated design.

What miscellaneous metals means

Miscellaneous metals, often shortened to misc metals, is the group of fabricated steel, stainless and aluminum items on a project that are not part of the load-carrying frame. On a specification it usually lives in Division 05, Metals. On a job site it is everything people touch: the stair tower, the access platform, the walkway, the handrail, the toeboard, the grating, the ladder, the pipe support, the equipment support, the bollard, the trench cover, the storage rack.

The category exists for a practical reason. The frame is designed by the engineer of record, drawn in the structural documents and priced from a tonnage take-off. The access steel is designed around how people and equipment will actually move through the plant, which is a question that is often not finished when the frame goes out to bid. So the two packages are separated, and the second one trails the first.

That separation is reasonable. The problem is what happens when nobody says out loud who owns the second package.

Why the package falls between two contracts

The gap is written into the standard the whole industry bids against. Section 2.2 of ANSI/AISC 303, the Code of Standard Practice for Steel Buildings and Bridges, states that structural steel “shall not include other steel, iron or metal items that are not generally described in Section 2.1, even where such items are shown in the structural design documents or are attached to the structural steel frame.”

Read that twice, because it is the sentence that causes the argument. Drawing a stair on the structural plan does not put the stair in the structural steel contract. AISC Design Guide 34, Steel-Framed Stairway Design, makes the same point in plain words: stairs and handrail are “other steel items” and therefore sit outside the scope of the Code of Standard Practice.

So when a bid form says “structural steel in accordance with the AISC Code of Standard Practice”, a steel fabricator who quotes exactly that is not being evasive by leaving out the stairs. The package has to be named. When it is not named, one of three things happens: three subcontractors each carry an allowance and the owner pays twice, nobody carries it and a change order lands late, or the general contractor buys the items piecemeal from whoever is still on site.

What is usually in the package

Scope varies by project, but an industrial miscellaneous metals package normally contains some combination of:

  • Access steel. Stair towers, individual stairs, landings, access platforms, walkways and crossovers.
  • Fall protection steel. Guardrail, handrail, toeboards, gate assemblies and the posts and base plates they land on.
  • Ladders. Fixed vertical ladders, cages, wells and the mounting brackets that attach them to tanks, vessels and buildings.
  • Walking surfaces. Grating, checker plate, stair treads and the clips and fasteners that hold them down.
  • Supports. Pipe supports, hangers and clamps, equipment supports and frames, cable tray supports, dunnage steel on roofs.
  • Protection and site items. Bollards, trench covers, access hatches, gas cylinder racks, lintels and embedded items.

LMC fabricates this category as a standing part of the structural scope. The published list on our structural steel page reads: miscellaneous metals, platforms, stairs, handrail and equipment supports. The fabrication facility lists access platforms and walkways; railings, stairs and cage ladders; piping supports and clamps; structural steel frame supports; and consumables and gas storage racks, in carbon and stainless steel, aluminum and alloy metals. When a package is drawing-driven rather than catalog-driven, it is handled as custom metal fabrication built to the drawings supplied.

The dimensions come from the code, not from preference

This is the part that separates miscellaneous metals from the rest of the steel on a project. A beam is sized by the engineer. A guardrail is sized by OSHA, and the numbers are specific.

In general industry, 29 CFR 1910.29 requires the top edge of top rails to be 42 inches plus or minus 3 inches above the walking-working surface, intermediate vertical members no more than 19 inches apart, and toeboards at least 3.5 inches high with no more than a quarter inch of clearance underneath. 29 CFR 1910.28 sets the trigger: protection is required wherever an employee is 4 feet or more above a lower level.

Stairs are just as prescriptive. 29 CFR 1910.25 requires standard stairs to be installed at 30 to 50 degrees from horizontal, with a maximum riser height of 9.5 inches, a minimum tread depth of 9.5 inches and a minimum width of 22 inches between vertical barriers. Landings must be at least as wide as the stair and at least 30 inches deep.

Fixed by regulation

Four numbers that size an access package

None of these is a design choice. Each one is a dimension or a date in the federal general industry standards, and each one has sent fabricated steel back to a shop when it was missed.

42 in ±3

Top rail height above the walking surface
guardrail systems, 29 CFR 1910.29(b)(1)

4 ft

Height at which fall protection is required
unprotected sides and edges, 29 CFR 1910.28(b)(1)(i)

30–50°

Allowed angle for standard stairs
from the horizontal, 29 CFR 1910.25(c)(1)

Nov 18, 2036

Deadline for fall arrest or ladder safety systems
all fixed ladders over 24 feet, 29 CFR 1910.28(b)(9)

Sources: OSHA 29 CFR 1910.25, 1910.28 and 1910.29, general industry walking-working surfaces.

There is a second set of numbers, and mixing them up is expensive. A stair that forms part of a building’s means of egress follows the building code, not the general industry standard, and the building code is tighter: the 2021 International Building Code caps risers at 7 inches and requires rectangular treads of at least 11 inches (Section 1011.5.2), with required guards at least 42 inches high (Section 1015.3).

Dimension OSHA standard stairs IBC egress stairs
Maximum riser 9.5 in 7 in
Minimum tread depth 9.5 in 11 in
Angle from horizontal 30 to 50 degrees set by riser and tread
Guard or top rail height 42 in ±3 42 in minimum

The same plant can contain both. A stair from the control room to an exit is an egress stair. A stair to a pump platform in the yard is an industrial stair. Fabricating the second one to the first one’s geometry wastes material and headroom; fabricating the first one to the second one’s geometry fails inspection. The specification should say which standard governs each item, by item.

Fixed ladders are on a clock

If a project involves existing tanks, vessels or silos, this one matters. Under 29 CFR 1910.28(b)(9), fixed ladders that extend more than 24 feet above a lower level must be equipped with fall protection. A cage or well is still acceptable on ladders installed before November 19, 2018. Ladders installed on or after that date need a personal fall arrest system or a ladder safety system, and by November 18, 2036 every fixed ladder over 24 feet must have one.

Cages are still fabricated, and there are good reasons to keep them on some installations. What changed is that on new work the cage is no longer the fall protection, so the ladder has to be detailed for a carrier rail or cable system from the start, with the mounting brackets and the engineered anchor points in the shop drawings rather than drilled in the field. On existing assets, the practical choice is often between retrofitting a ladder safety system and replacing the ladder with a stair, and that choice should be made before the steel is ordered.

Who designs the stair, and who stamps it

Most miscellaneous metals is delegated design. The engineer of record fixes the layout, the elevations and the loads. Somebody else designs the members, the connections and the anchorage, and in many jurisdictions that design is submitted under a licensed engineer’s seal. AISC Design Guide 34 recommends using the Code of Standard Practice as the framework for that delegated design of stairways, guards and handrail, even though those items sit outside the Code’s own scope.

Delegated design is a real cost and a real schedule item. It needs to be assigned in the contract documents, not discovered at submittal. Three questions settle it: who produces the design, who seals it, and who approves it. If the bid documents do not answer all three, every bidder prices the risk differently and the comparison between bids stops meaning anything.

Field dimensions, and why this package is always last

Handrail and stairs fit the structure that was erected, not the structure that was drawn. Columns go in within tolerance, which is not the same as going in exactly where the model put them. Concrete is poured within tolerance too. By the time the access steel has to land on both, the accumulated difference is real.

There are two honest ways to handle it. Hold the package until field measurements are taken, which is accurate and costs time. Or build adjustment into the details: slotted connections, field-welded posts, trim allowance on stringers and rails, with the final cut made on site. Most industrial projects use a mix, with the shop-built assemblies dimensioned from the field and the repetitive items built ahead.

What does not work is treating the package as a late catalog purchase. Grating sizes, stair stringers and handrail posts all have to agree with connections that are already in place, and a package bought without that coordination arrives needing rework before it can be installed.

Coating is decided before fabrication, not after

Access steel lives outdoors, gets walked on and takes boot traffic, so its coating decision is different from the frame’s. The two normal routes are a shop-applied paint system, or hot-dip galvanizing at a galvanizing plant.

Each has a schedule consequence. A painted package can be blasted and coated in the same shop that fabricated it, so it moves straight from weld-out to coating to shipping. A galvanized package leaves the fabricator, goes to the galvanizer, and comes back, which adds two shipping legs and a queue to the schedule. The decision also changes the details: galvanizing needs vent and drain holes designed in, and both routes need a stated plan for touching up field welds and bolted connections after erection. LMC blasts and coats in house, with NACE certified painters and blasters, so a painted package stays inside one schedule rather than three.

Fabricating and erecting the package under one contract

Miscellaneous metals is the package where the split between fabrication and erection hurts most, because almost every piece in it connects to something built by somebody else. When the same contractor fabricates the steel and sets it, a dimensional problem is found and corrected inside one organization instead of becoming a claim.

LMC self-performs both. Steel is fabricated at our Dansville, New York shop on a PythonX CNC plasma cutting system, a Ficep Gemini plate processor, CNC tube benders and automated welders, by AISC and AWS certified welders and fabricators working to AWS D1.1, with an AWS QC1 certified inspector and quality assurance manuals behind the work. The finished structures are sent to field crews for final assembly, with licensed and NCCCO trained crane operators and riggers handling the rigging. The same applies across our structural fabrication and construction services scopes.

In practice this package travels with the rest of the scope. On oil and gas work it is the platforms and ladders around compressor and meter stations, and the supports under the process piping. On power generation and data center work it is the access steel around skids, coolers and generators. Alongside civil work, it is the access steel that lands on the foundations and slabs once the concrete is finished.

What belongs in a miscellaneous metals bid package

A package that holds its price has these in it:

  • A named item list. Every stair, platform, ladder, rail run and support, with quantities or marked locations. Not “miscellaneous metals as required”.
  • The governing standard per item. OSHA general industry or the building code, stated item by item, so the geometry is not guessed.
  • Design responsibility. Who designs, who seals, who approves, and what the loads are.
  • Materials and finishes. Grating type and bearing bar direction, tread type, rail material and size, the coating system, and who performs field touch-up.
  • Fastener and anchorage specification. Including embedded items and whether anchor bolts are in this package or the concrete package.
  • Field measurement expectations. Who measures, when, and which assemblies are being held for it.
  • Delivery sequence. Tied to the erection schedule, not to a single delivery date, so access steel arrives when the structure is ready to receive it.
  • Inspection and documentation. Weld inspection requirements, submittals, and the turnover records the owner expects at the end.

Those eight items take an afternoon to write and remove most of the change orders this package is known for.

Frequently asked questions

What is included in miscellaneous metals?

Typically stairs, landings, access platforms and walkways, handrail and guardrail, toeboards, fixed ladders and cages, grating and checker plate, pipe and equipment supports, bollards, trench covers, hatches and embedded items. It is defined by exclusion: fabricated metal that is not part of the structural frame and is not supplied with a piece of equipment.

Is miscellaneous metals part of the structural steel contract?

Not by default. Section 2.2 of ANSI/AISC 303 states that structural steel does not include other steel, iron or metal items that fall outside its scope section, even where those items appear on the structural design documents or attach to the frame. If the package is meant to be in the steel contract, the contract has to say so and list the items.

How high does an industrial guardrail have to be?

In general industry, OSHA requires the top edge of the top rail to be 42 inches plus or minus 3 inches above the walking-working surface, with intermediate members no more than 19 inches apart. Where the walking surface is part of a building’s means of egress, the building code’s guard requirements apply instead, and the 2021 IBC requires a minimum of 42 inches.

Can a caged ladder still be installed?

A cage can be fabricated and installed, but on a fixed ladder extending more than 24 feet it no longer satisfies OSHA’s fall protection requirement for ladders installed on or after November 19, 2018. Those ladders need a personal fall arrest system or a ladder safety system, and existing ladders relying on cages have until November 18, 2036.

Should miscellaneous metals be galvanized or painted?

It depends on the exposure, the coating standard on the rest of the project and the schedule. Galvanizing adds a trip to and from a galvanizing plant and needs vent and drain holes designed in. A shop-applied paint system keeps fabrication and coating in one building, which is usually faster, and it can be matched to the rest of the structural package. Either way the decision belongs in the bid documents, together with who touches up field welds.

Getting the package priced

If you are putting an industrial project out to bid and the access steel is still described as an allowance, that is the line item to fix first. Send the drawings and the item list, and we will tell you what we would need to price the package and set it. Get in touch with the scope you have, even if it is not finished.